Monthly Archives: March 2007

JRC Construction Diary #11

img_2620.jpg

secondflr.jpg

Well, we’ve lucked out in the dry weather department! The concrete for the third floor was poured yesterday and the second floor was poured today. The picture on top shows the cement mixers sending the concrete through high powered hoses to the third floor. The next picture shows the workers laying out and smoothing the cement. The ground floor will take a little bit more time as more underground work needs to be done before the concrete is poured on.

Today I was given my first grand tour of the interior of the site by JRC President Alan Saposnik and construction supervisor Marc Bonnivier (that’s Marc on the left and me on right, below, standing against the west wall of the third floor sanctuary.)

Alan and I both agreed that the third floor sanctuary is already a sacred space. It felt like we were perched on a mountaintop, with a sublime quality of natural light suffused throughout. It was so powerful to contemplate the countless sacred memories that will soon be created in this makom kadosh – this holy place.

thirdflr1.jpg

JRC Construction Diary #10

construction-001.jpg

As you can see, the entire steel structure has now been completely covered by plastic tarps. (We’ve observed more than once that the building frame sort of resembles the Ohel Mo’ed – the ancient Israelite Tent of Meeting.) We’re currently waiting for the rainy weather to subside so the workers can pour the concrete for the floors.

The wet weather is continuing to delay the overall construction schedule, but we are hopeful that we can still make up time into the Spring and Summer. The forecast calls for the rain to subside – if this is the case, Marc the construction manager tells us they will be able to pour the third floor tomorrow.

The picture below gives a great view of the third floor sanctuary. The view faces east, from the back of the room toward the bimah. The east wall will be made almost entirely of glass, so the trees and sky will be clearly visible in back of the bimah and ark. You can also see the clerestory – clear glass panes that ring the top of the walls around the perimeter of the room. Needless to say, natural light will be a main feature of our new sanctuary.

Pray for sun!

construction-002.jpg

JRC Construction Diary #9

building-tarps1.JPG

It’s been a while since I’ve posted an update on our construction project. Here’s the latest:

Our progress has been slowed down somewhat due to the weather, which has been abysmal since January. We are currently about 19-20 days behind schedule, which is not that bad, considering how much snow, freezing rain, and high winds we’ve had to put with. Through it all, I’ve been consistently amazed at the stamina of the steelworkers, who will not miss a day unless it is absolutely impossible to be outside.

Now that the weather is comparatively milder, we hope to make up on some lost time. The workers are finishing up the final welding of all the steel griders and bolting metal decking on the floors of the structure. They’ve made literally thousands of welds to ensure the structural integrity of the building frame.

Next week workers will spot-drill holes in the steel where wiring and plumbing will eventually be installed, after which they will begin pouring the concrete for the floors. (If the weather is too cold, they will have to enclose the entire structure with tarps and heat the concrete with propane burners). By the end of the month, we hope to see our roof and walls in place.

The picture below gives you a good view of the arch for the main entry of the building, which will eventually be clad in Jerusalem stone.

We are still on track for LEED certification, and continue to aim for Gold level status. Stay tuned for more news on that front…

buildinjg-tarps2.jpg