There has been a fair amount of progress on our building over the last two weeks. All of the windows have been now been installed: the pic above shows the window framing for the east wall of the third floor sanctuary and the shot below shows the east window of the first floor chapel. The second pic down offers a good view of the windows in the second floor classrooms.

They have also begun polishing the concrete floors (you can see the workers doing just that in the sanctuary shot above.) We are told that this process will continue well into next week.

As I reported in my last diary entry, we have received the shipment of reclaimed cypress siding for the exterior walls. The contractors are still debating the best way to treat the wood before installing it, which will hopefully begin next week. The second pic from the bottom shows a test model of the cypress planks as they will look on the walls.

We have also just received the shipment of the Jerusalem stone (bottom pic) that will clad the entry arch and main interior wall. This installation should begin as soon as the concrete floor polishing is completed.

intchapel1.jpg

int1.jpg

cypress.jpg

jstone1.jpg