Author Archives: Rabbi Brant Rosen

Unknown's avatar

About Rabbi Brant Rosen

I'm a rabbi, blogger, and activist with a special interest in Israel/Palestine justice work.

JRC Construction Diary #14

img_27432.jpg

Here are a few photos from this week – nothing too dramatically different. The leaves are really getting thick on the treetops and the view from the sanctuary’s east window opening is incredibly green (above).

The main supply air duct (next pic down) has been installed from the roof down to the second floor, where we have our main fan system. It is going behind the opening that is being saved for a second elevator which we hope to install sometime in the future.

Our electric transformer from Commonwealth Edison was delivered this week (see bottom pic). Getting service from a utility can often be a challenge but they have been very cooperative with us and we are pleased to have the service on schedule.

img_27501.jpg

img_27511.jpg

JRC Construction Diary #13

A good productive week, helped by the beautiful sunny weather. See below: the first picture shows you the view toward the east window/wall of the bimah. The next two pix show the newly poured concrete on the ground floor. And finally, the component parts of our HVAC system (specifically, the heating/cooling coils) parked on the second floor.

sanc-view.jpg

ground-flr.jpg

ground-flr2.jpg

hvac.jpg

JRC Construction Diary #12

framing61.jpg

framing4.jpg

They have begun to install steel studs on the exterior walls, so our building is starting to look even more like a building now. This process should continue for a few more weeks, so in the meantime, enjoy the latest photo gallery:

The picture below shows the framing for the clerestory in the third floor sanctuary (note the treetops as they blossom into spring – this will be our view during services at this time of year!) The second picture from the bottom shows the first level – the workers plan to pour the concrete for the ground floor this Friday or early next week, depending as usual on the vagaries of the schedule and the cooperation of the weather. The picture on the bottom shows the duct work for the HVAC system, a key part of the energy efficiency component of the LEED process.

Speaking of which, our green building project continues to garner attention. I am proud to report that this Sunday, JRC’s will be the recipient of the first ever award given by the Network for Evanston’s Future in recognition of our green building efforts!

framing1.jpg

framing5.jpg

framing3.jpg

framing2.jpg

JRC Construction Diary #11

img_2620.jpg

secondflr.jpg

Well, we’ve lucked out in the dry weather department! The concrete for the third floor was poured yesterday and the second floor was poured today. The picture on top shows the cement mixers sending the concrete through high powered hoses to the third floor. The next picture shows the workers laying out and smoothing the cement. The ground floor will take a little bit more time as more underground work needs to be done before the concrete is poured on.

Today I was given my first grand tour of the interior of the site by JRC President Alan Saposnik and construction supervisor Marc Bonnivier (that’s Marc on the left and me on right, below, standing against the west wall of the third floor sanctuary.)

Alan and I both agreed that the third floor sanctuary is already a sacred space. It felt like we were perched on a mountaintop, with a sublime quality of natural light suffused throughout. It was so powerful to contemplate the countless sacred memories that will soon be created in this makom kadosh – this holy place.

thirdflr1.jpg

JRC Construction Diary #10

construction-001.jpg

As you can see, the entire steel structure has now been completely covered by plastic tarps. (We’ve observed more than once that the building frame sort of resembles the Ohel Mo’ed – the ancient Israelite Tent of Meeting.) We’re currently waiting for the rainy weather to subside so the workers can pour the concrete for the floors.

The wet weather is continuing to delay the overall construction schedule, but we are hopeful that we can still make up time into the Spring and Summer. The forecast calls for the rain to subside – if this is the case, Marc the construction manager tells us they will be able to pour the third floor tomorrow.

The picture below gives a great view of the third floor sanctuary. The view faces east, from the back of the room toward the bimah. The east wall will be made almost entirely of glass, so the trees and sky will be clearly visible in back of the bimah and ark. You can also see the clerestory – clear glass panes that ring the top of the walls around the perimeter of the room. Needless to say, natural light will be a main feature of our new sanctuary.

Pray for sun!

construction-002.jpg

JRC Construction Diary #9

building-tarps1.JPG

It’s been a while since I’ve posted an update on our construction project. Here’s the latest:

Our progress has been slowed down somewhat due to the weather, which has been abysmal since January. We are currently about 19-20 days behind schedule, which is not that bad, considering how much snow, freezing rain, and high winds we’ve had to put with. Through it all, I’ve been consistently amazed at the stamina of the steelworkers, who will not miss a day unless it is absolutely impossible to be outside.

Now that the weather is comparatively milder, we hope to make up on some lost time. The workers are finishing up the final welding of all the steel griders and bolting metal decking on the floors of the structure. They’ve made literally thousands of welds to ensure the structural integrity of the building frame.

Next week workers will spot-drill holes in the steel where wiring and plumbing will eventually be installed, after which they will begin pouring the concrete for the floors. (If the weather is too cold, they will have to enclose the entire structure with tarps and heat the concrete with propane burners). By the end of the month, we hope to see our roof and walls in place.

The picture below gives you a good view of the arch for the main entry of the building, which will eventually be clad in Jerusalem stone.

We are still on track for LEED certification, and continue to aim for Gold level status. Stay tuned for more news on that front…

buildinjg-tarps2.jpg

JRC Construction Diary #8

The frame of our new building is now complete. Take a look at the three pictures below: the top one shows a view of the site looking northeast. The middle picture shows an eastward view. (See the raised ceiling on on the third floor? That’s our sanctuary/social hall!) The bottom picture shows the signed beam (see previous diary entry) bolted into place in the second floor landing of the main stairwell.

img_2556.JPG

img_2558.JPG

img_2567.JPG

JRC Construction Diary #7

frame.jpg

The steel frame of our building has been going up all week and as of today it is almost complete. It is amazing to see how quickly the steel has been assembled. It is finally starting to look like a building!

Last Sunday JRC members gathered throughout the day to sign one of the steel beams. All day long folks dropped by to affix their names, messages, blessings, etc. that will become a permanent part of our synagogue structure.

It was a typically chilly Chicago day so we held the beam signing inside the construction trailer. Despite the cold weather (and the competing Bears playoff game) over 200 people dropped by to pick up a Sharpie and add their signatures to the beam!

The rest of the structure should be completed by next week. It’s not clear when our next communal ritual opportunity will take place, but knowing JRC, I’m sure we’ll think of something…

beam-signing1.JPG

JRC Construction Diary #6

steel.jpg

The first delivery of structural steel has arrived!

Now the construction crew will assemble the beams like an erector set, fastening and tightening the bolts, and eventually welding them into place. By the end of the week we should be able to see significant progress in the framework of our building.

This Sunday, we are having a congregation-wide “beam signing.” JRC members have been invited to write their names, messages, blessings, etc. on one of the steel beams before it is installed for posterity. True to form we never pass up an opportunity to gather together for ritual purposes…

JRC Construction Diary #5

foundation.jpg

The foundation is now complete! The workers have spent the week leveling off the site and believe it or not, the first shipment of structural steel will arrive this Monday. The next three weeks will be spent erecting the basic frame of the building. We are told it will go up very fast, in thirds, from the east side to the west, three stories at a time. By the end of January, we will have a very good idea of what the building will look like structurally.

If you are wondering why most of the ground in this picture still looks like so much dirt, it’s because the concrete slab that will provide the foundation floor will not be poured until March. Though the caissons, foundation walls and grade beams are firmly in place, the leveled ground needs to be left as bare earth for now so the workers can install the necessary underground plumbing, etc. The concrete for the third and second floors will actually be poured in place before the ground floor goes in.

Perhaps I’ll weigh in on the “Global Warming” vs. “El Nino” controversy in a future post. For now, let’s just say that the unseasonably warm weather has been kind to our construction project. We are still right on schedule.