Category Archives: Religion

JRC Construction Diary #20

img_3319.jpg

There has been some exciting progress on the building, so here’s one more post on the construction before we head off to Israel tomorrow…

The reclaimed cypress siding has started to go up on the exterior walls (see the second and third pix down). The siding will eventually get two coats of clear sealer which will protect and enhance the look of the wood. The Jerusalem stone is now going upon the main wall – the bottom pic shows some of the work that was done yesterday and today. (In case you are wondering, the small shadows on the the stones are made by the spacers that have been placed between the tiles to prepare them for grouting.)

As the pictures above and below indicate, the exterior of the building and the third floor sanctuary window are coming together beautifully. Looking forward to seeing even more progress when I get back to town August 15!

img_3307.jpg

img_3298.jpg

img_3301.jpg

img_3297.jpg

JRC Construction Diary #19

intsanc1.jpg

There has been a fair amount of progress on our building over the last two weeks. All of the windows have been now been installed: the pic above shows the window framing for the east wall of the third floor sanctuary and the shot below shows the east window of the first floor chapel. The second pic down offers a good view of the windows in the second floor classrooms.

They have also begun polishing the concrete floors (you can see the workers doing just that in the sanctuary shot above.) We are told that this process will continue well into next week.

As I reported in my last diary entry, we have received the shipment of reclaimed cypress siding for the exterior walls. The contractors are still debating the best way to treat the wood before installing it, which will hopefully begin next week. The second pic from the bottom shows a test model of the cypress planks as they will look on the walls.

We have also just received the shipment of the Jerusalem stone (bottom pic) that will clad the entry arch and main interior wall. This installation should begin as soon as the concrete floor polishing is completed.

intchapel1.jpg

int1.jpg

cypress.jpg

jstone1.jpg

JRC Construction Diary #18

img_3173-1.jpg

Our first shipment of cypress wood has arrived at the construction site – about half of the material that will serve as our exterior siding. The cypress is 100% reclaimed wood from barns in upstate New York (actually “mushroom houses,” to be completely specific.) After treating the wood with a clear sealer, they will start installing the siding hopefully by the end of the week.

The crew also expects to install the glass in the third floor clerestory on Monday, then proceed to the windows on the rest of the building. During the next few weeks, we should make significant progress on the building’s exterior and have a good sense of what it will eventually look like on the outside.

JRC Construction Diary #17

jrc-exterior-low-resolution.jpg

img_2937.jpg

The exterior of the building continues to take shape. I’ve juxtaposed the computerized rendering (top) with an actual exterior taken yesterday (next down) to give you a comparison of the virtual with the actual. Below, is a pic of the duct work and electric conduit, now installed in the first floor offices. The second pic from the bottom shows the rear stairs (termed the “Stairway to Heaven” by one contruction worker) that leads from the ground floor to the third floor sanctuary. The bottom pic offers a southward view on the third floor. The black pipe is the “rough-in” plumbing for the bathrooms. You can also see the main air duct and the yellow board enclosure that wraps around the elevator shaft.

We’re about five weeks behind schedule, but with good weather, we are still hoping for an early-Jan occupancy date. On the LEED front, we are currently safely in range for a Gold rating with the US Green Building Council and still have a fighting chance for Platinum (the highest rating!) The final determinant will ultimately come down to cost, but whatever happens, we are so very proud to be building synagogue so thoroughly infused with Green values…

img_2935.jpg

img_2903.jpg

img_2920.jpg

JRC Construction Diary #15

img_28471.jpg

Oh no! During a recent windstorm our neighbor’s tree was partially blown down, somewhat compromising the great leafy view from our sanctuary’s east window. We’re hoping against hope that the rest of the tree won’t have to be cut down.  In the meantime (as the pic below indicates) there’s still plenty of green to be seen as we look east…

img_28511.jpg

JRC Construction Diary #14

img_27432.jpg

Here are a few photos from this week – nothing too dramatically different. The leaves are really getting thick on the treetops and the view from the sanctuary’s east window opening is incredibly green (above).

The main supply air duct (next pic down) has been installed from the roof down to the second floor, where we have our main fan system. It is going behind the opening that is being saved for a second elevator which we hope to install sometime in the future.

Our electric transformer from Commonwealth Edison was delivered this week (see bottom pic). Getting service from a utility can often be a challenge but they have been very cooperative with us and we are pleased to have the service on schedule.

img_27501.jpg

img_27511.jpg

JRC Construction Diary #13

A good productive week, helped by the beautiful sunny weather. See below: the first picture shows you the view toward the east window/wall of the bimah. The next two pix show the newly poured concrete on the ground floor. And finally, the component parts of our HVAC system (specifically, the heating/cooling coils) parked on the second floor.

sanc-view.jpg

ground-flr.jpg

ground-flr2.jpg

hvac.jpg

JRC Construction Diary #12

framing61.jpg

framing4.jpg

They have begun to install steel studs on the exterior walls, so our building is starting to look even more like a building now. This process should continue for a few more weeks, so in the meantime, enjoy the latest photo gallery:

The picture below shows the framing for the clerestory in the third floor sanctuary (note the treetops as they blossom into spring – this will be our view during services at this time of year!) The second picture from the bottom shows the first level – the workers plan to pour the concrete for the ground floor this Friday or early next week, depending as usual on the vagaries of the schedule and the cooperation of the weather. The picture on the bottom shows the duct work for the HVAC system, a key part of the energy efficiency component of the LEED process.

Speaking of which, our green building project continues to garner attention. I am proud to report that this Sunday, JRC’s will be the recipient of the first ever award given by the Network for Evanston’s Future in recognition of our green building efforts!

framing1.jpg

framing5.jpg

framing3.jpg

framing2.jpg

JRC Construction Diary #11

img_2620.jpg

secondflr.jpg

Well, we’ve lucked out in the dry weather department! The concrete for the third floor was poured yesterday and the second floor was poured today. The picture on top shows the cement mixers sending the concrete through high powered hoses to the third floor. The next picture shows the workers laying out and smoothing the cement. The ground floor will take a little bit more time as more underground work needs to be done before the concrete is poured on.

Today I was given my first grand tour of the interior of the site by JRC President Alan Saposnik and construction supervisor Marc Bonnivier (that’s Marc on the left and me on right, below, standing against the west wall of the third floor sanctuary.)

Alan and I both agreed that the third floor sanctuary is already a sacred space. It felt like we were perched on a mountaintop, with a sublime quality of natural light suffused throughout. It was so powerful to contemplate the countless sacred memories that will soon be created in this makom kadosh – this holy place.

thirdflr1.jpg

JRC Construction Diary #10

construction-001.jpg

As you can see, the entire steel structure has now been completely covered by plastic tarps. (We’ve observed more than once that the building frame sort of resembles the Ohel Mo’ed – the ancient Israelite Tent of Meeting.) We’re currently waiting for the rainy weather to subside so the workers can pour the concrete for the floors.

The wet weather is continuing to delay the overall construction schedule, but we are hopeful that we can still make up time into the Spring and Summer. The forecast calls for the rain to subside – if this is the case, Marc the construction manager tells us they will be able to pour the third floor tomorrow.

The picture below gives a great view of the third floor sanctuary. The view faces east, from the back of the room toward the bimah. The east wall will be made almost entirely of glass, so the trees and sky will be clearly visible in back of the bimah and ark. You can also see the clerestory – clear glass panes that ring the top of the walls around the perimeter of the room. Needless to say, natural light will be a main feature of our new sanctuary.

Pray for sun!

construction-002.jpg