Category Archives: Green Buildings

JRC Construction Diary #22

img_3467-2.jpg

The Jerusalem stone has now been completely installed. The work this past week has now shifted to the main stairway on the south side of the building. The above pic shows the main stair risers that were installed last week. The stair pans (into which precast concrete will be placed) will be welded in place over the next few days. After the stairs are installed, the main exterior glass wall will set into place (likely late September or early October).

The pic below shows a view of the first floor interior – the reverse side of the stone wall – facing east toward the chapel. The big opening on the right side is a gift shop display case which faces the main office.

The next picture down shows us the north wall, which is the only exterior wall that is 100% finished with cypress siding. We are waiting for our last delivery of wood, which will allow us to finish the remaining three faces of the building.

The bottom pic shows the metal studs which have been installed on the first and second floors. The electricians are “roughing in” the conduit for outlets and switches and drywall will be added to the walls over the next couple of weeks.
img_3468-2.jpg

img_3483-2.jpg

img_3472-2.jpg

JRC Construction Diary #21

img_3405.jpg

While we were away in Israel these past two weeks, there was some nice progress on the building, though I am told the exterior work went somewhat more slowly because of some recent heavy rains. The pix above and below show the extensive work on the Jerusalem stone wall that runs along the south end of the building. This aspect of the project has been been critical as the workers cannot begin work on the main staircase until it is complete. The third pic down gives a good view of the cypress siding on the north wall, which has now been completed. They have also almost finished setting up the studs for the interior walls on the first and second floors (see bottom pic).

Looks like more rain is coming this week – thankfully we’re almost finished with the exterior work at this point…

img_3404.jpg

img_3418.jpg

img_3406.jpg

JRC Construction Diary #18

img_3173-1.jpg

Our first shipment of cypress wood has arrived at the construction site – about half of the material that will serve as our exterior siding. The cypress is 100% reclaimed wood from barns in upstate New York (actually “mushroom houses,” to be completely specific.) After treating the wood with a clear sealer, they will start installing the siding hopefully by the end of the week.

The crew also expects to install the glass in the third floor clerestory on Monday, then proceed to the windows on the rest of the building. During the next few weeks, we should make significant progress on the building’s exterior and have a good sense of what it will eventually look like on the outside.

JRC Construction Diary #17

jrc-exterior-low-resolution.jpg

img_2937.jpg

The exterior of the building continues to take shape. I’ve juxtaposed the computerized rendering (top) with an actual exterior taken yesterday (next down) to give you a comparison of the virtual with the actual. Below, is a pic of the duct work and electric conduit, now installed in the first floor offices. The second pic from the bottom shows the rear stairs (termed the “Stairway to Heaven” by one contruction worker) that leads from the ground floor to the third floor sanctuary. The bottom pic offers a southward view on the third floor. The black pipe is the “rough-in” plumbing for the bathrooms. You can also see the main air duct and the yellow board enclosure that wraps around the elevator shaft.

We’re about five weeks behind schedule, but with good weather, we are still hoping for an early-Jan occupancy date. On the LEED front, we are currently safely in range for a Gold rating with the US Green Building Council and still have a fighting chance for Platinum (the highest rating!) The final determinant will ultimately come down to cost, but whatever happens, we are so very proud to be building synagogue so thoroughly infused with Green values…

img_2935.jpg

img_2903.jpg

img_2920.jpg

JRC Construction Diary #16

img_2855.jpg

The workers have begun the process of putting plywood on the exterior of the building, which will be the first layer of its “outer skin.” The second pic from the bottom shows the installation of the rear stairs, which began Friday and will continue into next week.

As for our neighbors foliage (see last diary entry): alas, the entire tree needed to be cut down. Thankfully, as the pic on the bottom indicates, our third floor view is still quite lush.

img_2864.jpg

img_2856.jpg

img_2860.jpg

JRC Construction Diary #15

img_28471.jpg

Oh no! During a recent windstorm our neighbor’s tree was partially blown down, somewhat compromising the great leafy view from our sanctuary’s east window. We’re hoping against hope that the rest of the tree won’t have to be cut down.  In the meantime (as the pic below indicates) there’s still plenty of green to be seen as we look east…

img_28511.jpg

JRC Construction Diary #14

img_27432.jpg

Here are a few photos from this week – nothing too dramatically different. The leaves are really getting thick on the treetops and the view from the sanctuary’s east window opening is incredibly green (above).

The main supply air duct (next pic down) has been installed from the roof down to the second floor, where we have our main fan system. It is going behind the opening that is being saved for a second elevator which we hope to install sometime in the future.

Our electric transformer from Commonwealth Edison was delivered this week (see bottom pic). Getting service from a utility can often be a challenge but they have been very cooperative with us and we are pleased to have the service on schedule.

img_27501.jpg

img_27511.jpg

JRC Construction Diary #13

A good productive week, helped by the beautiful sunny weather. See below: the first picture shows you the view toward the east window/wall of the bimah. The next two pix show the newly poured concrete on the ground floor. And finally, the component parts of our HVAC system (specifically, the heating/cooling coils) parked on the second floor.

sanc-view.jpg

ground-flr.jpg

ground-flr2.jpg

hvac.jpg

JRC Construction Diary #12

framing61.jpg

framing4.jpg

They have begun to install steel studs on the exterior walls, so our building is starting to look even more like a building now. This process should continue for a few more weeks, so in the meantime, enjoy the latest photo gallery:

The picture below shows the framing for the clerestory in the third floor sanctuary (note the treetops as they blossom into spring – this will be our view during services at this time of year!) The second picture from the bottom shows the first level – the workers plan to pour the concrete for the ground floor this Friday or early next week, depending as usual on the vagaries of the schedule and the cooperation of the weather. The picture on the bottom shows the duct work for the HVAC system, a key part of the energy efficiency component of the LEED process.

Speaking of which, our green building project continues to garner attention. I am proud to report that this Sunday, JRC’s will be the recipient of the first ever award given by the Network for Evanston’s Future in recognition of our green building efforts!

framing1.jpg

framing5.jpg

framing3.jpg

framing2.jpg

JRC Construction Diary #11

img_2620.jpg

secondflr.jpg

Well, we’ve lucked out in the dry weather department! The concrete for the third floor was poured yesterday and the second floor was poured today. The picture on top shows the cement mixers sending the concrete through high powered hoses to the third floor. The next picture shows the workers laying out and smoothing the cement. The ground floor will take a little bit more time as more underground work needs to be done before the concrete is poured on.

Today I was given my first grand tour of the interior of the site by JRC President Alan Saposnik and construction supervisor Marc Bonnivier (that’s Marc on the left and me on right, below, standing against the west wall of the third floor sanctuary.)

Alan and I both agreed that the third floor sanctuary is already a sacred space. It felt like we were perched on a mountaintop, with a sublime quality of natural light suffused throughout. It was so powerful to contemplate the countless sacred memories that will soon be created in this makom kadosh – this holy place.

thirdflr1.jpg